DOTD gives update on LA 514 & LA 507 bridges

LA 514 bridge over Bayou Chicot in Red River Parish
Photo credit: DOTD social media

(UPDATE 3/24/2026): DOTD advises motorists that work continues on the replacement of the LA 514 bridge over Bayou Chicot in Red River Parish.

The contractor is currently working on completing the final bridge construction work, tying the roadway in to the new structure, and forming of the concrete barrier rail. Other activities include guardrail installation and permanent roadway striping.

At this time, the roadway is anticipated to reopen in mid-April 2026, weather and other factors permitting.

The other bridge currently under construction is the LA 507 bridge south of LA 514 near the Womack community. Barrier rail and other bridge work is progressing on this structure. It is anticipated to be complete in August 2026, weather and other factors permitting.

This $12 million project includes the replacement of six rural bridges in Red River in Bienville Parishes, and is a significant investment in ensuring the continued connectivity of the communities that utilize these bridges.